File #: 25-0625    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 1/7/2026 In control: Visalia City Council
On agenda: 1/20/2026 Final action:
Title: Award engineering design services - Authorize the City Manager to award and enter into a contract with Brandley Engineering for the engineering design project for the design phase of the Taxilane "A" and "B" and Hangar H3 Row 10 reconstruction project at Visalia Municipal Airport.
Attachments: 1. Professional Services Agreement, 2. Breakdown of Engineering Costs
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Wording:
title
Award engineering design services - Authorize the City Manager to award and enter into a contract with Brandley Engineering for the engineering design project for the design phase of the Taxilane "A" and "B" and Hangar H3 Row 10 reconstruction project at Visalia Municipal Airport.
body

Deadline for Action: None

Submitting Department: Administration - Airport

Contact Name and Phone Number:
Jody Miller, Airport Manager, (559)713-4282, Jody.Miller@Visalia.Gov
John Lollis, Assistant City Manager, (559)713-4323, John.Lollis@Visalia.Gov

Department Recommendation:
Staff recommends that the City Council authorize the City Manager to enter into a contract with Brandley Engineering for approved CIP project CP0573 for the design phase of the Taxilane "A" and "B" and Hangar H3 Row 10 reconstruction project at Visalia Municipal Airport.

Background Discussion:
As part of the approved Federal Aviation Administration (FAA) Airport Capital Improvement Plan, the FAA funds the rehabilitation, and if needed, replacement of communal aircraft movement areas at airports nationwide. This project is the design phase of the reconstruction of one of these areas (Taxilane "A" and "B" and Hangar H3 Row 10) at Visalia Municipal Airport.

At its meeting on August 4, 2025, the City Council acted to conditionally accept federal funds via an FAA grant in the amount of $134,520 that would fund the majority of the project, the remaining $7,080 will be split between state funds and airport funds.

At its meeting on November 17, 2025, the Council authorized a professional services agreement between the City and Brandley Engineering for the purpose of providing airport engineering design services and project management for a 5-year contract period. The projects that Brandley administers for the Airport, as well as the vast majority of the Airport's capital improvement program (CIP) projects, are federally funded. This project is included in exhibit A "Scope of ...

Click here for full text