File #: 25-0150    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 4/21/2025 In control: Visalia City Council
On agenda: 5/5/2025 Final action:
Title: Request Authorization to File Notice of Completion and Appropriation of Funds for Network Fiber Connectivity Project - Authorize the filing of a Notice of Completion the Network Fiber Connectivity at the Visalia Animal Care Center, and appropriate an additional $27,000 from the ARPA Fund.
Attachments: 1. Attachment 1_Location Map.pdf, 2. Attachment 2_Draft NOC.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Wording:
title
Request Authorization to File Notice of Completion and Appropriation of Funds for Network Fiber Connectivity Project - Authorize the filing of a Notice of Completion the Network Fiber Connectivity at the Visalia Animal Care Center, and appropriate an additional $27,000 from the ARPA Fund.
body

Deadline for Action: 5/5/2025

Submitting Department: Community Development

Contact Name and Phone Number:
Jonathan Frausto, Associate Engineer, jonathan.frausto@visalia.city, 713-4369
Dolores Verduzco, Financial Analyst, dolores.verduzco@visalia.city, 713-4540
Chris Crawford, City Engineer, chris.crawford@visalia.city, 713-4331
Jason Huckleberry, Engineering and Building Department Director, jason.huckleberry@visalia.city, 713-4495

Department Recommendation:
Staff recommends that the City Council authorize the filing of a Notice of Completion for the Network Fiber Connectivity at the Visalia Animal Care Center, CP0768, and appropriate an additional $27,000 from the American Rescue Plan Act (ARPA) Fund.
Background Discussion:
The project expanded the City's existing fiber optic infrastructure to the Visalia Animal Care Center to provide reliable network connectivity to the City's computer network resources. The Visalia Animal Care Center has been using a wireless microwave point to point connection since its construction in 2015. This connection has been unreliable, requiring frequent repairs impacting computer, internet, phone and day to day operations.

Change Orders:
The final cost of the construction contract including change orders is $148,294.92. Only one Change Order was processed in the amount to $2,794.92. Below is a summary of the contract change:

Change Order Breakdown To-Date

Category
Cost
Percentage
Errors & Omissions (E&O)
$0.00
0.00%
Utility Conflict (UT)
$0.00
0.00%
Balance of Quantities (BQ)
$0.00
0.00%
Unforeseen (UN)
$2,794.92
1.92%
Change of Scope (CofS)
$0.00
0.00%
Total:
$2,794.92
1.92%
Unforeseen (UN):
Du...