Department Recommendation: Staff recommends that the City Council approve and adopt the updated Sewer System Management Plan (SSMP) to maintain compliance with State and Regional Water Board requirements.
Summary:
The State Water Resources Control Board (SWRCB) requires all public agencies that own or operate sanitary sewer collection systems to prepare and maintain a Sewer System Management Plan (SSMP) under the Statewide General Waste Discharge Requirements for Sanitary Sewer Systems, Order No. 2022-0103-DWQ.
The SSMP provides a comprehensive plan for the proper management, operation, maintenance, and capacity assurance of the City's wastewater collection system to reduce the risk of sanitary sewer overflows (SSOs) and to protect public health and the environment.
The updated SSMP replaces the version previously adopted under Order No. 2006-0003-DWQ and brings the City into compliance with the revised 2022 General Order.
Background Discussion:
The City of Visalia owns and operates a wastewater collection system consisting of approximately 493 miles of gravity sewer pipelines, 13 lift stations, and associated force mains conveying wastewater to the Visalia Water Reclamation Facility.
Under Order No. 2022-0103-DWQ, the State Water Board requires that all enrollees update their SSMPs to align with the updated regulatory requirements outlined in Attachment D - Sewer System Management Plan Required Elements.
Public Works staff completed an internal audit and comprehensive update of the SSMP in 2025. The updated document includes new and revised elements addressing: