Skip to main content
Visalia Header
File #: 22-0023    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 1/14/2022 In control: Visalia City Council
On agenda: 2/7/2022 Final action:
Title: Request authorization to file a Notice of Completion for the intersection Improvements at County Center Street at Riggin Avenue and Giddings Street at Riggin Avenue. (Project Number 3010-72000/CP0459-999)
Attachments: 1. Location Map, 2. Owner Disclosure Form - American Paving
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Wording:
title
Request authorization to file a Notice of Completion for the intersection Improvements at County Center Street at Riggin Avenue and Giddings Street at Riggin Avenue. (Project Number 3010-72000/CP0459-999)

body
Deadline for Action: None

Submitting Department: Administration - CIP Engineering

Contact Name and Phone Number:
Diego Corvera, Civil Engineer, diego.corvera@vislia.city, 559-713-4209
Frank Senteno, City Engineer, frank.senteno@visalia.city, 559-713-4331
Nick Mascia, Assistant City Manager, nick.mascia@visalia.city, 713-4323

Department Recommendation:
Request authorization to file a Notice of Completion for the Intersection Improvements at County Center Street at Riggin Avenue and Giddings Street at Riggin Avenue Projects.

Background Discussion:
This project constructed two traffic signals at the intersections of County Center Street at Riggin Avenue and Giddings Street at Riggin Avenue which included the modification of the existing pedestrian ramps to meet the current Americans with Disabilities Act (ADA) criteria.

The traffic signal at Giddings Street and Riggin Avenue was designed and constructed in accordance with the ultimate design for the Riggin Widening project between Mooney Blvd and Conyer St. Temporary traffic transitions are currently in place to safe guard the existing SCE transmission poles which will be relocated as part of the Riggin Avenue widening project. We expect this relocation to take place in the Spring of 2023 or sooner.

The start of construction of the traffic signals began in April of 2021 and was completed in October 2021. The construction of the traffic signal and associated improvements were completed within the allotted construction timeline.

The final total project construction cost was $1,668,345.40. The construction contract was awarded to American Paving Co. in the amount of $1,458,855.00 in November of 2020. Prior to the award of the construction contract to American Paving C...