Authorize the City Manager to file a Notice of Completion for the construction of the FY 22-23 Reclamite Project (CIP 1410-72000/CP0248-999 & CIP 2730-72000/CP8358-999).
body
Deadline for Action: None.
Submitting Department: Administration - CIP Engineering
Contact Name and Phone Number:
Alejandro Ortega, Associate Engineer, alejandro.ortega@visalia.city, 713-4164
Chantha Chap, Civil Engineer, chantha.chap@visalia.city, 713-4418
Frank Senteno, City Engineer, frank.senteno@visalia.city, 713-4331
Nick Mascia, Assistant City Manager, nick.mascia@visalia.city, 713-4323
Department Recommendation:
Staff recommends that City Council authorize the City Manager to file a Notice of Completion for the FY 22-23 Reclamite Project.
Summary and Background:
The City currently utilizes multiple pavement preservations methods including, but not limited to Reclamite, Cape Seal, and Crack Seal. The streets are analyzed through the City's Pavement Management Program to determine cost-effective maintenance recommendations, while optimizing the expenditures of limited fiscal resources.
This annual Reclamite Project was developed based on a project list developed from the Pavement Management Program in combination with field investigations. To increase the longevity of pavement surfaces, it is imperative for the City to perform the correct preventative maintenance treatment to streets at the appropriate time. Applying Reclamite at this life-stage of the selected streets is beneficial as it extends the pavements life at a relatively inexpensive price. Without this preventive maintenance, as streets continuously deteriorate, future maintenance becomes more expensive and more time consuming.
This iteration of the Reclamite project focused on specific streets located in the Northeast quadrant of the City as shown in the attached map. The contractor, Talley Oil out of Madera, CA, completed the FY 22-23 Reclamite Project within budget and without any cha...