Legislation Details

File #: 26-0164    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 9/4/2026 In control: Visalia City Council
On agenda: 9/21/2026 Final action:
Title: Water Reclamation Facility laboratory HVAC and boiler replacement design services – Approve a professional services agreement with Lawrence Engineering Group for the Water Reclamation Facility laboratory HVAC and boiler replacement design services in the amount of $160,000, and appropriate an additional $52,000 from the Wastewater Fund.
Attachments: 1. 1. Sample Professional Services Agreement, 2. 2. Lawrence Engineering Group Proposal (dated July 16, 2026), 3. 3. Lawrence Engineering Group Revised Fees, Rates, Scope (dated September 4, 2026), 4. 4. RFP No. 25-26-14 with Addendum No. 1 and its attachments, 5. 5. Consultant Disclosure Form
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Wording:
title
Water Reclamation Facility laboratory HVAC and boiler replacement design services – Approve a professional services agreement with Lawrence Engineering Group for the Water Reclamation Facility laboratory HVAC and boiler replacement design services in the amount of $160,000, and appropriate an additional $52,000 from the Wastewater Fund.
body

Agenda Date: 09/21/2026

Prepared by:
Rehana Lustyan, Senior Project Manager | rehana.lustyan@visalia.gov | 559-713-4176
Ben Litwack, Public Works Manager | ben.litwack@visalia.gov | (559) 713-4671

Department Recommendation:
Staff recommends that the City Council to approve a professional services agreement with Lawrence Engineering Group (LEG) for design, assessment, and construction administration services for the Water Reclamation Facility (WRF) laboratory HVAC and boiler replacement project in the fixed amount of $160,000, and appropriate an additional $52,000 from the Wastewater Fund (431), and authorize the City Manager to execute the agreement and any related documents on behalf of the City.

Summary:
The Water Reclamation Facility (WRF) Laboratory requires replacement of aging HVAC and boiler systems, including assessment of mechanical, electrical, structural, and controls components. The City issued RFP No. 252614 to retain a consultant to evaluate existing conditions, design replacement systems, prepare construction documents, provide bid support, and perform construction administration. Lawrence Engineering Group (LEG) was selected as the topranked consultant. Staff has completed scope clarification and fee negotiations, and the final fixed fee of $160,000 reflects all required design phases, temporary HVAC coordination, structural and electrical modifications, Pelican EMS integration, reimbursables, and construction administration. Staff recommends award of the contract so project design can begin.

Background Discussion:
The WRF Laboratory’s existing HVAC and boiler systems cons...