Title: Award Construction and Construction Management Contract- Authorize the City Manager to award the construction contract for the Caldwell Avenue Widening Project from Santa Fe Street to Lovers Lane to Avison Construction, Inc. in the amount of $14,741,768 and execute an agreement with Vanir Construction Management, Inc. to provide the construction management services for the Caldwell Avenue Widening Project from Santa Fe Street to Lovers Lane in the amount of $480,090.
Attachments: 1. 01-Map of Project Area, 2. 02-RFB 24-25-16 Bid Summary Tabulation, 3. 03-Avison Owner Discl Stmt, 4. 04-Vanir CM_Owner Disclosure, 5. 05-C21045-Vanir 2024
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Wording:

title

Award Construction and Construction Management Contract- Authorize the City Manager to award the construction contract for the Caldwell Avenue Widening Project from Santa Fe Street to Lovers Lane to Avison Construction, Inc. in the amount of $14,741,768 and execute an agreement with Vanir Construction Management, Inc. to provide the construction management services for the Caldwell Avenue Widening Project from Santa Fe Street to Lovers Lane in the amount of $480,090.

body

Deadline for Action:  11/18/2024

 

Submitting Department: Community Development

 

Contact Name and Phone Number:
Eric Bons, Senior Civil Engineer, Eric.Bons@visalia.city, (559) 713-4350
Dolores Verduzco, Financial Analyst, Dolores.Verduzco@visalia.city, (559) 713-4540 Chris Crawford, City Engineer, Chris.Crawford@visalia.city, (559) 713-4331
Jason Huckleberry, Engineering & Building Director, Jason.huckleberry@visalia.city, (559) 713-4495

 

 

Department Recommendation:

Staff recommends City Council:

1.                     Authorize the City Manager to award the construction contract for RFB 24-25-16, Caldwell Avenue Widening Project from Santa Fe Street to Lovers Lane to Avison Construction, Inc. in the amount of $14,741,768.00, and

2.                     Authorize the City Manager to execute an agreement with Vanir Construction Management, Inc. to provide the construction management services for the Caldwell Avenue Widening Project from Santa Fe Street to Lovers Lane in the amount of $480,090.00.

 

 

Background Discussion:

This is a roadway widening project for Caldwell Avenue from Santa Fe Street to Lovers Lane (Rd. 140) which will widen Caldwell Avenue from 2-lanes to 4-lanes with a raised center median, median landscaping, curb, gutter, storm drain system, sanitary sewer main extension, sidewalk, and a joint use pathway.  The County of Tulare also has a project for Caldwell Avenue (Ave. 280) from Lovers Lane to S. Virginia Avenue widening from 2-lanes to 4-lanes.  The widening of Caldwell Avenue (Ave. 280) within the City of Visalia and the County of Tulare is part of a regional corridor enhancement project from Highway 99 to the City of Exeter to ease congestion along this corridor. 

 

 

Award of Construction Contract:

RFB 24-25-16 was advertised beginning October 2, 2024.  Bids were opened on October 31, 2024, with the submitted bid amounts listed from lowest to highest. 

 

 

Contractor

Location

Bid Amount

1.

Avison Construction, Inc.

Madera, CA

$14,741,768.00

2.

Yarbs Grading & Paving, Inc.

Fowler, CA

$15,125,638.73

3.

Archer civil Construction LLC

Tulare, CA

$16,697,776.15

4.

Teichert Construction

Fresno, CA

$17,964,822.00

5.

Granite Construction Company

Fresno, CA

$19,468,538.76

 

Avison Construction, Inc. submitted the apparent low bid of $14,741,768.00.  City staff has reviewed the bid documents and found them to be complete and acceptable.  As part of the review process, the references provided by Avison Construction, Inc. have been verified.  The responses from each reference were favorable and demonstrated that Avison Construction, Inc. can perform the work for this project. 

 

Construction Management (CM) Services.

In order to obtain construction support services to continue to successfully and timely deliver the construction of various Capital Improvement Project (CIPs), the Purchasing Division issued a request for Proposals (RFP 20-21-18) to retain up to three (3) qualified consulting firms to provide Construction Management (CM)/Resident Engineering (RE) services on an on-call basis.  The City reviewed seven (7) proposals in response to the solicitation.  A selection committee reviewed and ranked each proposal to develop a short-list of 3 firms.  Those three (3) firms then presented to an interview panel early in December 2020. The interview panel ranked each team and selected NV5, Inc., 4Creeks, Inc., and Vanir Construction Management, Inc., as the highest ranked consultants.   This on-call list is valid for five (5) years and is renewed annually.  This list will need to be re-established by the end of 2025.

 

Vanir Construction Management, Inc. was selected for the construction management services because the other two construction management firms were recently awarded the construction management services for other City of Visalia projects or the construction management firm was also the design engineering firm for this particular project. 

 

The construction management services include an overall constructability review, public outreach, general construction management and coordination services, and project closeout services.  The duration for the construction services is estimated to be 14 months.

 

The project construction documents require the contractor to maintain a single lane of travel in both the eastbound and westbound directions along Caldwell Avenue throughout construction.  Vanir Construction Management Inc. will be managing public outreach and working with the contractor to minimize traffic impacts during construction to ensure the safety of the motoring public.

 

Although not anticipated, if during construction it is determined that a closure is necessary, appropriate public notification will be coordinated with the contractor and the construction management firm to efficiently notify the public and establish traffic detours accordingly.

 

Fiscal Impact:

The funding for this construction contract and the construction management services are accounted for within the overall project budget.  The details of the project budget and the estimated project expenses are shown in the table below.  The estimated project expenses take into account the environmental processes, various permitting fees, design costs, right of way, construction management, construction testing and inspection, construction surveying and staff time.

 

This project is funded by multiple accounts.

 

Project Budget:

 

Measure R Regional (Fund 133)

 

$19,431,780

Measure R Local (Fund 131)

 

$783,300

Senate Bill1 - Local Partnership Program (Fund 281) - ROW phase

 

$400,000

Senate Bill1 - Local Partnership Program (Construction Phase)

 

$3,844,000

Total Project Budget Estimate

 

$24,459,080

 

Estimated Project Expenditures:

 

Environmental Process

 

$50,000

Design and Right-of-Way

 

$3,979,231

4 Creeks Contract (Design, RW, & Const. Eng.)

$1,539,231

 

Estimate City Design & RW Support

$325,000

 

RW Estimate

$1,600,000

 

Estimate Pole Relocation at Burke Street

$140,000

 

Estimate Culvert Permits

$325,000

 

Estimate Electrical Service

$50,000

 

Construction Cost Estimates

 

$18,846,858

Construction Bid (Avison Construction)

$14,741,768

 

Construction Management (Vanir)

$480,090

 

Est. Construction Testing

$250,000

 

Estimate City Construction Staff & Misc. Const.

$250,000

 

Estimate Construction Surveying/Staking

$125,000

 

Construction Contingency (20%)

$3,000,000

 

Total Project Estimate

 

$22,876,089

 

 

 

Estimated Budget Surplus/(Deficit)

 

$1,528,991

 

There are sufficient project funds available, therefore no appropriation of funds is required at this stage of the project.  The surplus of funding is due to the actual construction bid being lower than the engineer’s construction estimate by approximately $1,300,000 and anticipated savings in other related construction costs.  This money will remain with the project due to the size and complexity of the project.

 

Prior Council Action:
October 7, 2024:  City Council accepted an update on the real property negotiations for the properties needed for the Caldwell Avenue Widening from Santa Fe Street to Lovers Lane Project (CP8268). 

June 3, 2024:  City Council authorized the City Manager to execute a cooperative agreement for reimbursement with the County of Tulare for the installation of a sewer main in Avenue 280 (Caldwell Avenue) from Lovers Lane (Rd. 140) to Rd. 144 and the appropriation of $535,000 from the Wastewater Trunkline Fund (231). 

April 1, 2024:
                      City Council accepted an update on the real property negotiations for the properties needed for the Caldwell Avenue Widening from Santa Fe Street to Lovers Lane Project (CP8268). 

December 18, 2023:  City Council accepted an update on the real property negotiations for the properties need for the Caldwell Avenue Widening form Santa Fe Street to Lovers Lane Project (CP8268). 

September 18, 2023:  City Council accepted an update on the real property negotiations for properties needed for the Caldwell Avenue Widening from Santa Fe Street to Lover Lane Project (CP8268)  

August 7, 2023:  City Council adopted a Resolution of Necessity to acquire property and temporary construction easements for portions of eight separate properties along Caldwell Avenue between Santa Fe Street and Lovers Lane for the purpose of widening Caldwell Avenue (CP8268). 

June 5, 2023:  City Council accepted a update on the real property negotiations for properties needed for the Caldwell Avenue Widening from Santa Fe Street to Lovers Lane Project (CP8268). 

November 21, 2022:  City Council accepted an update on the real property negotiations for properties needed for the Caldwell Avenue Widening from Santa Fe Street to Lovers Lane Project (CP8268).  

October 4, 2021:  Council accepted and authorized an appropriation of $1,387,000 from the Senate Bill 1 - Local Partnership Program (SB1-LPP) for the Caldwell Avenue Widening from Santa Fe to Lovers Lane Project (CP8268) 

September 21, 2020:  Council authorized approval of Amendment Number 2 with 4 Creeks Inc. in the amount of $489,755.00 bringing the contract from $768,000.00 to $1,257,755.00 for additional services related to the Caldwell Avenue Widening from Santa Fe to Lovers Lane (CP8268) 

April 20, 2020:  Council authorized amending the Measure R Supplemental Agreement for the Caldwell Avenue Widening from Santa Fe to Lovers Lane (CP8268) due to increase in the scope of work. 

May 2, 2016:  Council authorized a contract with 4 Creeks Engineering Co. for RFP 15-16-49 to prepare Plans, Specifications, and Estimate for the Caldwell Avenue Widening from Santa Fe to Lovers Lane.   

November 21, 2022:  Council, in closed session, approved property appraisals and authorized City staff and consultant to purchase properties with authority to pay up to twenty percent above appraised value.

 

Other: None.

 

Alternatives:
Reject all bids and potentially forfeit $3,844,000 of Senate Bill1 - Local Partnership Program funding for the construction of this project. 

 

Recommended Motion (and Alternative Motions if expected):

recommendation

I move to authorize the City Manager to enter into a contract with Avison Construction, Inc. for RFB 23-24-16 for the Caldwell Avenue Widening Project from Santa Fe Street to Lovers Lane in the amount of $14,741,768.00; and authorize the City Manager to execute an agreement with Vanir Construction Management, Inc. to provide the construction management services for the Caldwell Avenue Widening Project from Santa Fe Street to Lovers Lane in the amount of $480,090.00.

end

 

Environmental Assessment Status: 
The environmental assessment has been completed.

 

CEQA Review: 
Completed - Conducted by the County of Tulare for the Avenue 280 (Caldwell Avenue) Corridor Enhancement Project.

 

Attachments:
A.
                     Map of Project Area 
B.
                     RFB 24-25-16 Bid Summary Tabulation
C.
                     Avison Construction, Inc. Ownership Disclosure Form
D.
                     Vanir Construction Management, Inc. Ownership Disclosure Form
E.
                     Vanir Construction Management On Call Contract