Visalia Header
File #: 25-0073    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 3/12/2025 In control: Visalia City Council
On agenda: 4/7/2025 Final action:
Title: Visalia Parkway Widening Notice of Completion - Request authorization to file a Notice of Completion for the Visalia Parkway Widening at Mooney Boulevard Improvement Project.
Attachments: 1. 01-Project Loc Map, 2. 02-RFB 22-23-28 Owner Disclosure Stmt_Avison
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Wording:

title

Visalia Parkway Widening Notice of Completion - Request authorization to file a Notice of Completion for the Visalia Parkway Widening at Mooney Boulevard Improvement Project.

 

body

Deadline for Action:  4/7/2025

 

Submitting Department: Community Development

 

Contact Name and Phone Number:
Eric Bons, Senior Civil Engineer, Eric.Bons@visalia.city, (559) 713-4350
Chris Crawford, City Engineer, Chris.Crawford@visalia.city, (559) 713-4331
Jason Huckleberry, Engineering & Building Director, Jason.Huckleberry@visalia.city, (559) 713-4495

 

Department Recommendation:

Staff requests City Council authorize the City Manager to file a Notice of Completion for the Visalia Parkway Widening at Mooney Boulevard Improvement Project.

 

Background Discussion:

The Visalia Parkway Widening at Mooney Boulevard Improvement project constructed the roadway improvements to Visalia Parkway at Mooney Boulevard which included the modification of the existing traffic signal at the intersection and improvement to Mooney Boulevard.  The project constructed Visalia Parkway to its ultimate width for an arterial roadway, matching the roadway improvements constructed by the two commercial development projects that were constructed concurrently at the southeast and southwest corners of this intersection.  

 

The modifications to the existing traffic signal at Visalia Parkway and Mooney Boulevard provided two lanes of travel in each direction as well as dual left turns within Visalia Parkway at Mooney Boulevard.  The roadway improvements made to Mooney Boulevard provided a dedicated right-turn lane for the northbound traffic. The commercial development at the southwest corner of this intersection also constructed Visalia Parkway along their project frontage west of Mooney Boulevard.  The commercial development at the southeast corner of this intersection extended Visalia Parkway easterly beyond the City’s project limits along the commercial development frontage. These three projects were coordinated through the design and construction phases to ensure all the work blended together.

 

The original construction contract was awarded to Avison Construction in the amount of $1,804,237.00.  The final construction cost included a construction change for a total project construction cost of 1,829,905.95.  The total construction change orders amounted to $25,128.95 or 1.39%.  The following is a breakdown of the construction change order. 

 

Errors & Omissions (E & O)

$ 0

0.00%

Utilities (UT)

$ 0

0.00%

Balance of Quantities (BQ)

$ 845.94

0.05%

Unforseen Conditions (UN)

$ 4,269.10

0.24%

Owner Directed Change in Scope (CoS)

$ 20,013.91

1.11%

TOTAL:

 $ 25,128.95

1.39%

 

Balance of Quantities:

The total quantity of hot mix asphalt placed by the contractor increased by an additional 6.13 tons and the additional quantity was paid at the contract unit price for hot mix asphalt. 

 

Unforseen Conditions:

The contractor discovered an existing 18” storm drainpipe during the construction process and this 18” storm drainpipe was realigned to connect to a new storm drain inlet located at the northeast corner of Visalia Parkway and Mooney Boulevard. 

 

Owner Directed Change in Scope:

The commercial development at the southeast corner of Visalia Parkway and Mooney constructed the required improvements to Visalia Parkway east of the City’s limits of work at the same time as the City’s contractor was constructing the adjacent roadway improvements, so the City removed the temporary roadway transition from the City contractor’s scope of work.  This resulted in a credit to the project due to the removal of the construction of a roadway transition.  Added work was needed to modify existing manholes, additional nighttime work, construction of a transition of Visalia Parkway west of Mooney Boulevard with additional traffic control as well as additional striping, and the replacement of sidewalk to construct an ADA compliant pedestrian ramp.

 

Fiscal Impact:

The Visalia Parkway Widening at Mooney Boulevard Improvement Project (CP0408) is funded by multiple sources and the budget summary is shown below. 

 

 

Project Funding:

 

 

 

Measure R Local Fund (131)

  $1,640,000

 

Transportation Impact Fee Fund (241)

     $935,000

 

Total Project Funding:

  $2,575,000

 

 

 

Project Cost:

 

 

 

Design Consultant Contract

     $155,435

 

Design Staff Time

       $71,000

 

Traffic Signal Equipment (purchased by City)

       $73,513

 

Potholing for location of underground utilities

       $42,000

 

Construction Contract

   $1,804,777

 

Construction Change Order

        $25,129

 

Material Testing

        $12,140

 

City Surveying, Con. Mngmt., Inspection, & misc.

      $100,000

 

Total Project Cost:

   $2,283,994

 

 

 

Summary:

 

 

 

Project Funding:

   $2,575,000

 

Project Cost:

  ($2,283,994)

 

Approximate Funding Remaining:

      $291,006

 

Any funds remaining will be returned to the fund from which they originated.

 

Prior Council Action:
November 11, 2022, Authorize the City manager to award the construction contract for the widening of the intersection of Visalia Parkway at Mooney Boulevard to Avison Construction of Madera, CA in the amount of $1,804,777.

July 20, 2020,
Authorize the City Manager to award a professional design services contract to 4Creeks, Inc. for the design of the traffic signal improvements and roadway improvements for the Visalia Parkway at Mooney (SR-63) in the amount of $139,945.

 

Other:
None

 

Alternatives:
None Recommended

 

Recommended Motion (and Alternative Motions if expected):

recommendation

Authorize the City Manager to file a Notice of Completion for the Visalia Parkway Widening at Mooney Boulevard Improvement Project.

end

Environmental Assessment Status: 
Completed

 

CEQA Review: 
Mitigated Negative Declaration No. 2021-42

 

Attachments:
1.  Project Location Map
2.  Contract Disclosure form.