Legislation Details

File #: 24-0080    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 2/28/2024 In control: Visalia City Council
On agenda: 3/18/2024 Final action:
Title: Playground Award - Authorize the City Manager to award a contract to Playground Design & Installation Services at Riverbend Park to Anchor 41 Construction, of Hanford, CA, for an amount not to exceed of $272,129.00.
Attachments: 1. RFP 22-23-68 Playground Design Install Services for Riverbend Park, 2. RFP-22-23-68 Addendum 1 (002), 3. Anchor 41 Proposal - Riverbend, 4. PROPOSAL EVALUATION FORM RFP-22-23-68, 5. Riverband Park Committee Score Totals Eval 1, 6. Riverbend Park Committee Score Totals Eval 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Wording:

title

Playground Award - Authorize the City Manager to award a contract to Playground Design & Installation Services at Riverbend Park to Anchor 41 Construction, of Hanford, CA, for an amount not to exceed of $272,129.00.

body

 

Deadline for Action:  3/18/2024

 

Submitting Department: Community Services

 

Contact Name and Phone Number: Daryl Tillman, Park Maintenance Supervisor 713-4435; daryl.tillman@visalia.city <mailto:daryl.tillman@visalia.city> Alvin Dias, Parks and Facilities Manager 713-4564; alvin.dias@visalia.city <mailto:alvin.dias@visalia.city> 

 

Department Recommendation:

It is recommended that the City Council authorize the award of a construction contract for the installation of new playground equipment at Riverbend Park to Anchor 41 Construction, of Hanford, CA, in the amount of and not to exceed $272,129.00, per specifications of RFP 22-23-68.                                               

 

Background Discussion:

At the December 20, 2021 City of Visalia Council Work Session, City Council approved the appropriation of $29,364,455 from the American Rescue Plan Act (ARPA), of which $3,900,000 was appropriated for citywide park improvements. There are several park projects that are slated to be completed with these funds, such as shade structures, arbor replacement, updated park amenities, and park playground replacement. Staff identified six parks that needed playground replacement due to age, vandalism, or the ability to obtain replacement parts. Riverbend Park is the first of the six parks to go through the RFP process.

 

RFP #22-23-68 was advertised on 10/26/2023 and 11/02/2023, for the design, demo, and construction of a new play structure within the dimensions of the existing playground fall surfacing area. Two proposer conferences were conducted on November 7, 2023, and November 8, 2023, where staff answered questions and toured the playground area with several contractors. Proposals for the RFP were due on November 29, 2023. The City received a total of five design submissions from three proposers. A selection committee was formed and met on December 21, 2023, to review the design proposals and select the design they felt met the requirements of the RFP and gave the most playability to the community. The selection committee was comprised of four City staff members Daryl Tillman, Katrina Bonds, Julia Kirkman, and Zach Huff. These members were selected for the review committee to gain several different perspectives of the submitted designs, from both a maintenance and parent with small children’s standpoints.

 

The selection committee reviewed the designs in a two-part process. The first review of the proposals that were submitted used the design criteria that was established in RFP #22-23-68. During their review the committee felt that the proposals submitted by Anchor 41 Construction and R. E. Schultz Option 1 had the top two designs. Staff then submitted the results to the Purchasing Division and the sealed cost proposals were released to the selection committee for review. The selection committee then reviewed the cost for each of the top two designs and concluded that the Anchor 41 design proposal was the overall winner that best meets the requirements of RFP #22-23-68 and the needs of the community.

 

 

Fiscal Impact:

The fiscal impact for RFP 22-23-68 a construction contract for Playground Design & Installation Services at Riverbend Park is funded by the American Rescue Plan Act (ARPA) Fund 642, of which $3,900,000.00 has been budgeted.

 

Prior Council Action: None

 

Other: None

 

Alternatives: Reject proposals and go out for another Request for Proposals.

 

Recommended Motion (and Alternative Motions if expected):

recommendation

I move to award a contract for the Playground Structure Replacement Project at Riverway Sports Park, to Anchor 41 Construction, (RFP 22-23-68) for a not to exceed amount of $275,129.00.

end

Environmental Assessment Status:  N/A

 

CEQA Review:  N/A

 

Attachments: RFP 22-23-68, RFP 22-23-68 Addendum 1, Anchor 41 Construction Proposal, Evaluation Form, Committee Score Totals.