Legislation Details

File #: 24-0300    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 7/22/2024 In control: Visalia City Council
On agenda: 8/5/2024 Final action:
Title: Award Riggin Avenue Widening Project: Authorize the City Manager to award the construction contract with Cen-Cal Construction for Riggin Ave Widening Mooney Blvd to Conyer St. in the amount of $6,480,000.00; authorize the transfer of Measure R Regional funds; authorize the appropriation of additional Transportation Impact Fee and Measure R Regional funds; and authorize the amendment to the Measure R Supplemental Agreement.
Attachments: 1. Cen Cal Ownership Disclosure Form, 2. Project Location, 3. Riggin Widening Projects Location Map
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Agenda Item Wording:

title

Award Riggin Avenue Widening Project: Authorize the City Manager to award the construction contract with Cen-Cal Construction for Riggin Ave Widening Mooney Blvd to Conyer St. in the amount of $6,480,000.00; authorize the transfer of Measure R Regional funds; authorize the appropriation of additional Transportation Impact Fee and Measure R Regional funds; and authorize the amendment to the Measure R Supplemental Agreement.

body

Deadline for Action:  None

 

Submitting Department: Community Development

 

Contact Name and Phone Number:

Diego Corvera, Senior Civil Engineer, Diego.Corvera@visalia.city, 713-4209

Dolores Verduzco, Financial Analyst, Dolores.Verduzco@visalia.city, 713-4540

Jason Huckleberry, Engineering and Building Department Director, Jason.Huckleberry@visalia.city, (559) 713-4495

 

Department Recommendation:

Staff recommends that the City Council:

1.                     Authorize the City Manager to award a contract with Cen-Cal Construction for RFB 23-24-09 for the Riggin Avenue Mooney Blvd to Conyer St (3010-72000/CP0398-999) in the amount of $6,480,000.00; and

2.                     Authorize the transfer of Measure R Regional (133) funds of $500,000 from the Riggin Ave Widening - Akers to Demaree (CP0397) to the Riggin Ave Widening - Mooney to Conyer Project (CP0473); and

3.                     Authorize an appropriation of additional Transportation Impact Fee (241) funds in the amount of $50,000; and

4.                     Authorize an appropriation of additional Measure R Regional (133) funds in the amount of $2,771,000; and

5.                     Authorize the City Manager to amend the Measure R Supplemental Agreement.

 

Background Discussion:

The Riggin Avenue widening project, from Mooney to Conyer Street, will reconfigure Riggin Avenue to a 4-lane divided roadway. The project will also modify the intersection of Riggin Ave at Giddings St as a protected intersection, completing it to its ultimate configuration and incorporate a frontage road on the south side of Riggin Ave.

The purpose of the “Riggin Avenue Widening Project” is to increase vehicle capacity on Riggin Avenue by adding additional east/west lanes and to provide for an efficient flow of traffic in support of the increase in development within the surrounding area. In addition, the City Council identified this segment of Riggin Avenue from Mooney Boulevard to North Conyer Street as a priority transportation corridor as it was part of the “Ring-Road” concept previously identified in various City reports. 

 

The Council, at their June 21st, 2021, meeting directed staff to award the design contract to 4Creeks Inc. and accepted and appropriated $2.4 million from the Federal High Improvement Program (HIP) funds for the construction of the “Riggin Avenue Widening Project” from North Mooney Boulevard to North Conyer Street.

 

Frontage Road Prior Approval

Council and the local community approved the construction of a local frontage road (Council meeting August 1st, 2022) along this stretch of Riggin Avenue to separate the Riggin Avenue fronting residents from direct access to Riggin Avenue, allowing for safer ingress and egress from their homes. 

This frontage road improvement will add concrete corner island infrastructure, similar to what is used in a protected intersection configuration, on the southside of the intersection of Riggin Ave at Giddings St to funnel the local frontage road traffic away from the intersection.  This configuration will be modified and mirrored on the northside of the intersection to create a fully protected intersection to improve safety for all modes of travel.

 

Protected Intersection Prior Approval

Council and the local community approved the construction of a Protected Intersection (Council meeting February 21st, 2023) at Riggin Ave and Giddings St to improve the safety of bicyclist and pedestrians traversing the intersection.

The Protected Intersection will add concrete corner island infrastructure, as well as conspicuous striping and signage at the intersection of Riggin Ave at Giddings St to define the multi modal nature of the intersection.

 

Bidding Process:

Staff advertised RFB 23-24-09 for the Riggin Ave Widening Mooney Blvd to Conyer St closed Wednesday, June 12th, 2024.  The project was split with the “Base Bid” encompassing the plan delineated improvements and an “Additive Alternate” relating to sidewalk construction on the southside of Riggin Ave. This project received five (5) bids, below are the three (3) lowest responsive bidders:

 

 

 

 

Base Bid + Additive Alternate

 

Contractor

Location

Bid Amount

1

Cen Cal Construction

Bakersfield, CA

$6,480,000.00

2

American Paving

Fresno, CA

$6,607,778.00

3

Cal Valley Construction

Fresno, CA

$6,851,038.21

Base Bid

 

Contractor

Location

Bid Amount

1

Cen Cal Construction

Bakersfield, CA

$6,267,477.51

2

American Paving

Fresno, CA

$6,558,357.90

3

Cal Valley Construction

Fresno, CA

6,643,348.72

 

City Staff proceeded to review all five (5) bids submitted and found the apparent 1st lowest bidder “Yarbs Grading and Paving Inc” submitted an incomplete bid.  Yarbs Grading submitted a bid package missing three (3) bid items; without these the final construction bid tabulation was significantly lower than their proposed bid price.  Yarbs formally withdrew their bid acknowledging their error.

Cen Cal Construction’s bid proposal was determined to be the lowest responsive bid after the review process; the references provided by Cen Cal Construction Inc. have been verified.  The references provided included the City of Wasco, Kern County Public Works Dept, and City of Bakersfield. These refereces were called by City staff with favorable responses from all jurisdictions. As a result, Staff recommends that the construction contract be awarded to Cen Cal Construction Inc.

 

Riggin Avenue Projects Status:

-                     Riggin Avenue widening from Kelsey St to Shirk St

o                     Design Completed

o                     Construction Fall 2024 (Utility Relocation Spring 2025)

-                     Riggin Avenue widening Shirk to Roeben (Developer Driven)

o                     Construction Fall 2024 (Utility Relocation Spring 2025)

-                     Riggin Avenue widening Roeben to Akers

o                     Currently in design, awaiting 30% design submittal

o                     Construction early 2026

-                     Riggin Avenue widening from Akers St to Demaree St

o                     Construction Completed 2024

-                     Riggin Avenue Widening from Mooney Blvd to Conyer St. (Subject Project)

o                     Construction Fall 2024 (Anticipated Completion Summer 2025)

 

Refer to attached Riggin Widening Project exhibit, for project locations.

 

 

 

Fiscal Impact:

The Riggin Ave Widening project Mooney Blvd to Conyer St is funded using Highway Improvement Program (HIP) grant funds through the Federal Highway Administration (FHWA), and funds from the Measure R Regional (133) Fund and the Transportation Impact Fee (241) Fund. See below the project funding breakdown.

 

Riggin Avenue Widening Mooney Blvd to Conyer St CIP0473

Project Funding Source

 

Measure R Regional Funds (133)

$200,000

Transportation Impact Fee (241)

$2,254,000

Highway Improvement Program (HIP) Funding (281)

$2,485,000

Total Project Funding

$4,939,000

 

 

Estimated Project Costs

 

Project Management

$109,400

Design Services

$314,000

Utility Relocation

$188,000

Fire Hydrant Installation

$170,600

Construction

$6,480,000

Construction Contingency (10%)

$648,000

Construction Management (Estimate)

$100,000

Construction Services (Materials Testing, Inspection (Est), Survey)

$250,000

Total Estimated Project Costs

$8,260,000

 

 

Surplus (Deficit)

($3,321,000)

 

 

Transfer & Appropriation of Funds

 

Transfer - Measure R Regional (133) from Riggin - Akers to Demaree (CP0397)  to Riggin - Mooney to Conyer (CP0473)

$500,000

Appropriate - Transportation Impact Fee (241)

$50,000

Appropriate - Measure R Regional (133)

$2,771,000

Total Transfer & Appropriation of Funds

$3,321,000

 

Measure R Regional Funds

Staff recommends transferring project cost savings realized from the completion of the Riggin from Akers to Demaree segment in the amount of $500,000 to the Riggin from Mooney to Conyer segment.

 

Due to the above-identified budget deficit, staff recommends an additional appropriation in the amount of $2,771,000 from Measure R Regional for the completion of this project.

 

Staff has coordinated with TCAG, previously making them aware of the expected deficit and need to increase the Measure R Regional contribution in order to complete the project. An amendment to the Measure R Supplemental Agreement is needed to increase the Measure R Regional funds allocated towards this project.

 

 

Prior Council Action:

February 21, 2023

Authorized the City Manager to proceed with the design and construction of a bicycle Protected Intersection at the Riggin Avenue and Giddings Street associated with the Riggin Widening Project Mooney Blvd. to Conyer St and for staff to develop guidelines that evaluate these intersection treatments at future locations on a case by case basis and to proceed with implementation.

 

December 5, 2022

Authorized the City Manager to approve payment to California Water Service in the amount of $150,259.00 for the installation of five fire hydrants and two irrigation services as part of the Riggin Widening project between Mooney Blvd to Conyer St and appropriated an additional $85,000 in Highway Infrastructure Program (HIP) funds.

 

September 19, 2022

Authorized the City Manager to execute the Southern California Edison (SCE) Joint Use Agreement (JUA) and adopted Resolution 2022-52 for the Riggin Widening project between Mooney Blvd to Conyer Street.

 

August 1, 2022

Received a staff presentation on the proposed local frontage road to be constructed with the Riggin Avenue Widening Project Mooney Blvd to Conyer Street.

 

June 20, 2022

Adopt Resolutions 2022-39 and 2022-40, designating a portion of City owned property located within 2 Parcels, Lot “A” of Highland Park Estates subdivision and Lot “A” of Highland Park, Unit No. 2 subdivision as part of the public City Street System respectively.

 

May 16, 2022

Adopt Resolution 2022-33 authorizing the City Manager to execute Southern California Edison (SCE) Utility Agreement No. CP0473-SCE2592 for the Riggin Widening project between Mooney Blvd to Conyer Street.

 

 

April 18, 2022

Adoption Resolution No. 2022-27 certifying Mitigated Negative Declaration No. 2022-16 prepared for California Environmental Quality Act (CEQA) compliance as part of the Highway Infrastructure Program (HIP) funding for the construction of the “Riggin Avenue Widening Project” from North Mooney Boulevard to North Conyer Street (State Clearing house No. 2022030456) (Resolution No. 2022-27 required).

 

June 21, 2021

Authorize the City Manager to award a sole source professional design services contract to 4Creeks, Inc., for the design of the “Riggin Avenue Widening Project” from North Mooney Boulevard to North Conyer Street, and appropriation of funds to establish a preliminary project budget.

 

Recommended Motion (and Alternative Motions if expected):

recommendation

I move to Authorize the City Manager to enter into a contract with Cen-Cal Construction for RFB 23-24-09 Riggin Ave Widening Mooney Blvd to Conyer St Project (3010-7200/CP0473-999), in the amount of $6,480,000.00, authorize the transfer of $500,000 of Measure R Regional funds from CP0397 to CP0473; authorize the additional appropriation of Transportation Impact Fee funds in the amount of $50,000 and Measure R Regional funds in the amount of $2,771,000; and authorize the City Manager to amend the Measure R Supplemental Agreement.

end

Environmental Assessment Status:

Adopted Mitigated Negative Declaration No. 2022-16

 

Attachments:

1.                     Cen Cal Construction Inc. Ownership Disclosure Form

2.                     Project Location Map