File #: 24-0503    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 11/8/2024 In control: Visalia City Council
On agenda: 12/3/2024 Final action:
Title: Request Authorization to File Notice of Completion: Authorize the filing of a Notice of Completion for FY 22-23 Measure N Street Rehab - County Center St. from Houston Ave. to Riggin Ave. Project.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Agenda Item Wording:

title

Request Authorization to File Notice of Completion: Authorize the filing of a Notice of Completion for FY 22-23 Measure N Street Rehab - County Center St. from Houston Ave. to Riggin Ave. Project.

body

 

Deadline for Action:  None

 

Submitting Department: Community Development

 

Contact Name and Phone Number:

Diego Corvera, Senior Civil Engineer, diego.corvera@visalia.city, 713-4209

Dolores Verduzco, Financial Analyst, dolores.Verduzco@visalia.city, 713-4540

Chris Crawford, City Engineer, chris.crawford@visalia.city, 713-4331

Jason Huckleberry, Engineering and Building Department Director, Jason.Huckleberry@visalia.city, (559) 713-4495

 

Department Recommendation:

Staff recommends that the City Council authorize the filing of a Notice of Completion for the FY 22-23 Measure N Street Rehab - County Center St. from Houston Ave. to Riggin Ave. Project (CIP 3010-72000/CP0599-99).

 

Background Discussion:

The FY 22-23 Measure N Street Rehab - County Center St. from Hoston Ave. to Riggin Ave. Project consisted of paving County Center St. from Houston Ave. to Riggin Ave. (1.0 miles). The pavement rehabilitation work included removing isolated areas of pavement failures, also known as digouts, edge grinding of existing asphalt, and overlaying with asphalt and a paving mat. 

The project upgraded some of the existing curb ramps to meet current Americans with Disabilities Act (ADA) requirements. The project also replaced the Class II bike lanes with a Class IV bike facility that included enhanced bike lane infrastructure, with the construction of a protected intersection at Ferguson Ave. and County Center St.

 

Change Orders:

The final cost of the construction contract including change orders is $1,844,695.47.  Two Change Orders were processed totaling in a credit of $64,426.53 against the project.  Below is a summary of the contract change orders:

 

 

 

 

Change Order Breakdown To-Date

 

Category

Cost

Percentage

Errors & Omissions (E&O)

$0.00

0.00%

Utility Conflict (UT)

$0.00

0.00%

Balance of Quantities (BQ)

($72,301.87)

-3.79%

Unforeseen (UN)

$0.00

0.00%

Change of Scope (CofS)

$7,875.34

0.41%

Total:

($64,426.53)

0.41%

 

Balance of Quantities (BQ)

The final construction quantities for various bid items were overestimated during design and this reduction resulted in a credit against the project.

Change of Scope:

During the project construction staff determined the need to expand the project scope in order to satisfy ADA compliance requirements and accessible transitions.  The additional scope included additional concrete sidewalk improvements and modifications to curb ramps.  This additional work was included in construction change one, refer to the fiscal impact section for project budget.

 

Fiscal Impact:

This project was funded using Measure N (fund 141) and Gas Tax (Fund 111).

 

FY 22-23 Measure N Street Rehab - County Center St Houston Ave to Riggin Ave

Project Budget

 

Measure N Funds (Fund 141)

$2,246,950.00

Gas Tax (Fund 111)

$254,900.00

Total Project Funding

$2,501,850.00

Estimated Project Costs:

 

Design Cost (Staff Time)

$48,500

Construction Cost

$1,909,122.00

Construction Change Orders

($64,426.53)

Construction Services (Material Testing, Inspection, Survey)

$83,000

Total Project Costs:

$1,976,195.47

Surplus (Deficit)

$525,654.53

 

The final cost of the construction contract including change orders is $1,844,695.47 with only two Change Order’s processed resulting in a credit of $64,426.53 against the project.

 

Upon the close out phase of the project, there will remain a project surplus of approximately $526,000.  The surplus funds will be returned to the originating funding source.

 

 

 

Prior Council Action:

September 18, 2023

City Council authorized the City Manager to award the construction contract for FY 22-23 Measure N Street Rehab - County Center from Houston Ave. to Riggin Ave. (RFB 22-23-62), to Avison Construction of Madera, CA. in the amount of $1,909,122 and appropriated $254,900 from Gas Tax Fund (111) (CIP 1410-72000/CP0599-999).

 

November 7, 2022

Staff presentation received on the proposed Bicycle Lane Enhancement as part of the County Center Drive Rehabilitation.

 

Recommended Motion (and Alternative Motions if expected):

recommendation

I move to Authorize the filing of a Notice of Completion for the FY 22-23 Measure N Street Rehab - County Center St. from Houston Ave. to Riggin Ave. Project (CIP 1410-72000/CP0599-999).

end

 

Environmental Assessment Status:

Categorical Exemption

 

CEQA Review:

Categorical Exemption, Class 1, Section 15301c

 

Attachments:

NA