Legislation Details

File #: 25-0101    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 3/26/2025 In control: Visalia City Council
On agenda: 4/21/2025 Final action:
Title: Riggin Avenue Project Award & Transfer of Funds: Authorize the City Manager to award the construction contract with Agee Construction Corporation for the Riggin widening project from Kelsey St. to Shirk St. in the amount of $8,098,281.00; authorize the transfer of Measure R Regional funds; and the amendment to Measure R Supplemental Agreements.
Attachments: 1. Agee Owner Disclosure Form, 2. Location Map, 3. Draft Contract
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Agenda Item Wording:

title

Riggin Avenue Project Award & Transfer of Funds: Authorize the City Manager to award the construction contract with Agee Construction Corporation for the Riggin widening project from Kelsey St. to Shirk St. in the amount of $8,098,281.00; authorize the transfer of Measure R Regional funds; and the amendment to Measure R Supplemental Agreements. 

body

 

Deadline for Action:  4/21/2025                     

 

Submitting Department: Engineering and Building Department

 

Contact Name and Phone Number:

Diego Corvera, Senior Civil Engineer, Diego.Corvera@visalia.city, 713-4209

Dolores Verduzco, Financial Analyst, Dolores.Verduzco@visalia.city, 713-4540

Chris Crawford, City Engineer, Chris.Crawford@visalia.city, 713-4331

Jason Huckleberry, Engineering and Building Department Director, Jason.Huckleberry@visalia.city, 713-4495

 

Department Recommendation:

Staff recommends that the City Council:

1.                     Authorize the City Manager to award a contract with Agee Construction Corporation for RFB 23-24-61 for the Riggin Avenue Widening Project Kelsey Street to Shirk Street 3010-72000/CP0398-999 in the amount of $8,098,281.00; and

2.                     Authorize the transfer of Measure R Regional  (133) funds of $2,565,000 from the Riggin Ave. Widening from Roeben St. to Akers St. project (CP0628) to the Riggin Ave. Widening from Kelsey St. to Shirk St. project (CP0398); and

3.                     Authorize the City Manager to amend the Measure R Supplemental  Agreements.

 

Background Discussion:

The Riggin Avenue Widening Project spans from Kelsey St to Shirk St and consists of widening the existing 2-lane street to a divided 4-lane street with the construction of center medians, median landscaping, street lighting, interconnect conduit, storm drainage, turn pockets, Class IV bike lanes, and the signalization of Riggin Ave. and Shirk St.

 

Industrial and residential development in the surrounding areas has increased significantly over the past ten years, resulting in greater traffic congestion in this area of the City. The widening of this segment of Riggin Avenue between Kelsey Street and Shirk Street will help alleviate this congestion. Additionally, the proposed traffic signal at the intersection of Riggin Avenue and Shirk Street will help with access to the SR 198 and SR 99 interchanges along those respective roadways.

 

This project will be constructed concurrently with the Shirk Capacity Enhancement Project from School Ave. to Riggin Ave. and the Carleton Acres Commercial Development project at the northeast corner of the Shirk and Riggin intersection.   

 

Traffic Impacts:

The project construction documents require the contractor to maintain a single lane of travel in both the east and westbound direction along Riggin Avenue throughout construction.  A construction management firm has been hired by the City to manage public outreach and to work with the contractor to minimize traffic impacts during construction and assist with monitoring the safety of the motoring public. 

 

Bidding Process:

Staff advertised RFB 23-24-61 for the Riggin Avenue Widening Project from Kelsey St. to Shirk St. beginning February 3rd, 2025 and the RFB closed Tuesday, March 11th, 2025.  This project received the following seven (7) bids:

 

Base Bid

 

Contractor

Location

Bid Amount

1

Agee Construction Corporation

Clovis Ca

$8,098,281.00

2

Yarbs Grading and Paving Inc.

Fresno, CA

$8,440,112.00

3

Cen-Cal Construction

Bakersfield, CA

$8,647,211.00

4

Avison Construction

Madera, CA

$8,990,010.00

5

Cal Valley Construction Inc.

Fresno, CA

$9,107,394.80

6

Archer Civil Construction

Tulare, CA

$9,388,440.69

7

Granite Construction Company

Fresno, CA

$9,701,025.50

 

City Staff proceeded to review all seven (7) bids submitted and Agee Construction Corporation’s bid proposal was determined to be the lowest responsive bid as part of the review process. The references provided by Agee Construction Corp. have been verified.  The references provided included County of Fresno, City of Fresno, and City of Visalia.  These references were called by City staff with favorable responses from all jurisdictions.  As a result, Staff recommends that the construction contract be awarded to Agee Construction Corp.

Fiscal Impact:

Riggin Avenue Widening project is a multi-funded project with funds budgeted from Transportation Impact Fee (241), Measure R Regional Fund (133), and an Economic Development Administration grant.

 

See the project funding breakdown for the project below.

 

 

 

 

Riggin Avenue Widening Project Kelsey to Shirk Budget

Riggin Avenue Project Budget (CP0398)

 

Measure R Regional Funds (Fund 133)

$1,700,000

Traffic Impact Fee (Fund 241)

$4,775,000

Economic Development Administration Grant

$4,000,000

Total Project Funding

$10,475,000

Estimated Project Costs:

 

Project Management & Misc.

$200,000

Design Services

$375,000

Acquisition Services

$29,000

Land Acquisition (Right-of-way)

$1,107,000

Utility Relocation (SCE relocation Agreement)

$1,200,000

Construction (Agee Construction Corp)

$8,098,281

Construction Contingency (10% of Construction)

$809,828

Traffic Signal Pole and Equipment Purchase

$250,000

Construction Management ~(3.5%)

$280,000

Construction Services (Material Testing, Inspection, Survey) ~ (8.5%)

$690,000

Total Estimated Project Costs:

$13,039,109

Surplus (Deficit)

($2,564,109)

Round to

($2,565,000)

Transfer from Riggin Widening - Roben to Akers (CP0628)

$2,565,000

 

Due to the above-identified budget deficit, staff recommends the transfer of $2,565,000 of Measure R Regional (133) funds from the Riggin Widening from Roeben to Akers project to the Riggin Widening from Kelsey to Shirk project. An amendment to the Measure R Supplemental Agreements for the projects is needed to transfer Measure R Regional funds between projects.

 

This shortfall is due to increasing construction cost as well as a $1.8M Measure R Regional transfer prior to other Riggin projects to address shortfalls that were seen on those project.

 

City Council approved on January 21, 2025, the submission of Congressional Community Project Funding requests for the 2025-26 Fiscal Year to include a request of $4 million towards the widening of Riggin Avenue. If approved, funding will be allocated towards the Riggin Widening from Roeben to Akers project to backfill the Measure R funds being transferred to the Riggin Widening from Kelsey to Shirk project. If the Congressional request is not filled, Measure R Regional funds will be used for the project.

 

Prior Council Action:

October 21, 2024

Council Authorized the City Manager to execute an agreement with NV5, Inc. to provide construction management services for two City projects 1) Shirk Street Capacity Enhancement Project from School Ave to Riggin Ave and 2) Riggin Avenue Widening Project from Kelsey St to Shirk St in the amount of $545,707.60 & $259,369.23 respectively, combined total of $805,076.83

 

August 5, 2024

Council authorized the execution of Southern California Edison (SCE) Facilities Relocation Agreement for $1,081,000.00 and adopt resolution 2024-46 for the Riggin Avenue Widening Project  Kelsey St to Shirk St. Project.

 

October 17, 2022

Council accepted grant award from the U.S. Economic Administration (EDA) for $4,000,000 and executed the EDA grant agreement for the construction of Riggin Avenue Widening project from Kelsey St to Shirk St.

 

March 21, 2022

Adopted resolution No. 2022-09 certifying Mitigated Negative Declaration No. 2021-62 prepared for CEQA compliance as part of the Economic Development Administration (EDA) ARPA Grant for construction of the Riggin Widening Project from Kelsey Street to Shirk Street (State clearing house No. 2022010046) (Resolution No. 2022-09 required).

 

March 15, 2021

Conference with Real Property Negotiators (Pursuant to G.C. Section 54956.8 Property: Portion of APN 077-200-006 generally located at the northwest corner of the intersection of Riggin Avenue and Shirk Street.

 

Conference with Real Property Negotiators (Pursuant to G.C. Section 54956.8 Property: Portion of APN 077-100-088 generally located at the northeast corner of the intersection of Riggin Avenue and Shirk Street.

 

Conference with Real Property Negotiators (Pursuant to G.C. Section 54956.8 Property: Portion of APN 077-480-001 generally located at the northwest corner of the intersection of Riggin Avenue and Kelsey Street.

 

September 8, 2020

Conference with Real Property Negotiators (Pursuant to G.C. Section 54956.8 Property: Portion of APN 077-480-001 generally located at the northwest corner of the intersection of Riggin Avenue and Kelsey Street.

 

August 17, 2020

Council authorized the City Manager to enter into a contract with 4Creeks Inc., for RFP 19-20-60 to prepare Plans, Specifications, Estimates, and Environmental Services for the Riggin Avenue Widening Project from Kelsey Street to Shirk Street, in the amount not to exceed $200,000.00.

 

April 6, 2020

Council authorized the execution of a measure R Supplement Agreement with the Tulare County Association of Governments (TCAG) to secure $3.5 million of Measure R Regional Funds for the Riggin Ave. Widening from Kelsey St to Shirk

 

Recommended Motion (and Alternative Motions if expected):

recommendation

I move to Authorize

1.                     The City Manager to award a contract with Agee Construction Corporation for RFB 23-24-61 for the Riggin Avenue Widening Project Kelsey Street to Shirk Street 3010-72000/CP0398-999 in the amount of $8,098,281.00; and

2.                     The transfer of Measure R Regional  (133) funds of $2,565,000 from the Riggin Ave Widening from Roeben St. to Akers St. project (CP0628) to the Riggin Ave. Widening from Kelsey St. to Shirk St. project (CP0398); and

3.                     The City Manager to amend the Measure R Supplemental  Agreements as stated in this report.

end

 

Environmental Assessment Status:

CEQA Exemption

 

Attachments:

1.                     Agee Construction Corporation Ownership Disclosure Form

2.                     Project Location Map

3.                     Draft Contract