File #: 26-0193    Version: 1
Type: Public Hearing Item Status: Agenda Ready
File created: 9/28/2026 In control: Visalia City Council
On agenda: 10/19/2026 Final action:
Title: Urgency Ordinance extension – Consideration of extending Ordinance No. 2026-10, an interim urgency ordinance adopted as a temporary moratorium on the acceptance, processing, approval, or issuance of permits and entitlements for new data center developments and communications equipment buildings within the City of Visalia pursuant to California Government Code Section 65858 for an additional ten (10) months and fifteen (15) days (4/5’s approval of the City Council is required for passage of Ordinance No. 2026-12).
Attachments: 1. Adopted Urgency Ordinance 2026-10, 2. Extending Temporary Moratorium Ordinance No. 2026-12, 3. PowerPoint Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Wording:
title
Urgency Ordinance extension – Consideration of extending Ordinance No. 2026-10, an interim urgency ordinance adopted as a temporary moratorium on the acceptance, processing, approval, or issuance of permits and entitlements for new data center developments and communications equipment buildings within the City of Visalia pursuant to California Government Code Section 65858 for an additional ten (10) months and fifteen (15) days (4/5’s approval of the City Council is required for passage of Ordinance No. 2026-12).
body

Agenda Date: 10/19/2026

Prepared by:
Paul Bernal, Planning and Community Preservation Director, (559) 713-4025, paul.bernal@visalia.gov; James Koontz, City Attorney

Department Recommendation:
Staff recommends that the City Council extend Ordinance No. 2026-10, an urgency ordinance placing a temporary moratorium on the acceptance, processing, approval, or issuance of permits and entitlements for new data center development and communications equipment buildings while the City continues to research and analyze recent state legislation and land use regulations governing new data centers within the City of Visalia pursuant to California Government Code Section 65858 (4/5’s approval of the City Council is required for passage of Ordinance No. 2026-12).
If adopted, the urgency ordinance will be extended for an additional ten (10) months, fifteen (15) days from the date of its adoption pursuant to Government Code section 65858.

Summary:
On September 8, 2026, the City Council adopted Ordinance No. 2026-10, which enacted a moratorium on the acceptance, processing, approval, or issuance of permits and entitlements for new data center development and communications equipment buildings, while the City considers land use regulations governing new data centers within the City of Visalia pursuant to California Government Code Section 65858. In addition, on October 5, 2026, the City Council received a staff report regarding the m...

Click here for full text