Legislation Details

File #: 25-0665    Version: 1
Type: Consent Item Status: Passed
File created: 2/4/2026 In control: Visalia City Council
On agenda: 2/17/2026 Final action: 2/17/2026
Title: Designate City owned property into public right of way - Adopt Resolution 2026-03 designating City owned property located at the northwest corner of Roeben Street and Howard Avenue into the public right of way system.
Attachments: 1. Attachment A - Legal Description, 2. Attachment B - ROW Exhibit, 3. Elliott Subdivision Phase 1 Recorded Final Map, 4. Resolution 2026-03
Agenda Item Wording:
title
Designate City owned property into public right of way - Adopt Resolution 2026-03 designating City owned property located at the northwest corner of Roeben Street and Howard Avenue into the public right of way system.
body

Agenda Date: 02/17/2026

Prepared by:
Jason Huckleberry, Director of Eng and Building, (559) 713-4495, Jason.huckleberry@visalia.gov

Department Recommendation:
Staff recommends that the City Council adopt Resolution 2026-03, designating City owned property located at the northwest corner of Roeben Street and Howard Avenue into the public right of way system.

Summary:
San Joaquin Valley Homes, the developer of the Elliott Subdivision Phase 1, including a 4.1-acre City owned park parcel, has coordinated with Southern California Edison (SCE) to provide essential utility infrastructure near and around the developer's residential subdivision and City park parcel. SCE's approved plans provide power to the new residential development and the future City park but require additional City property be dedicated for public right of way to ensure SCE facilities can be installed properly. The City owned property being converted into public right of way is a landscape outlot adjacent to Roeben street that was dedicated with the Elliott Phase 1 final map.

This dedication of City owned property is being requested in lieu of providing a specific SCE easement that they have requested. The dedication of public right of way for the areas described in Attachment A & B provides SCE with full rights as conveyed in existing franchise agreements.


Background Discussion:
On August 19, 2025, the Elliott Subdivision Phase 1 final map was recorded, subdividing the 25.4-acre area into 83 residential lots and an approximate 4.1-acre parcel dedicated to the City of Visalia for a future neighborhood park. The development project has progressed and is preparing to install final electrical facilities for the residential development, whic...

Click here for full text