File #: 24-0442    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 10/9/2024 In control: Visalia City Council
On agenda: 10/21/2024 Final action:
Title: Approve Agreement with California Dairies, Inc. - Approve the agreement with California Dairies, Inc. (CDI) to allow them to increase their permitted wastewater discharge flow capacity and decrease their biochemical oxygen demand under their Industrial Discharge Permit utilizing a fee exchange.
Attachments: 1. CDI Exhibit A, 2. CDI Exhibit B, 3. CDI Exhibit C, 4. Rates and Fees FY24-25, 5. CDI Agreement, 6. CDI - Agreement Calculation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Agenda Item Wording:
title
Approve Agreement with California Dairies, Inc. - Approve the agreement with California Dairies, Inc. (CDI) to allow them to increase their permitted wastewater discharge flow capacity and decrease their biochemical oxygen demand under their Industrial Discharge Permit utilizing a fee exchange.
body

Deadline for Action: 10/21/2024

Submitting Department: Public Works

Contact Name and Phone Number: Ben Litwack, Public Works Manager, (559)713-4671, ben.litwack@visalia.city

Department Recommendation:
Staff recommends that Council approve the agreement with California Dairies, Inc. (CDI) to allow them to increase their permitted wastewater discharge flow capacity and decrease their biochemical oxygen demand under their Industrial Discharge Permit utilizing a fee exchange subject to any minor conforming changes acceptable to the City Manager and City Attorney.

Background Discussion:
California Dairies, Inc. (CDI) is a significant industrial sewer discharger within the City. Their Visalia facility is their largest in the State and specializes in butter and milk powder production. CDI's current average daily permitted flow discharge limit is 1.87 million gallons per day (MGD), however they consistently exceed that limit with an average daily discharge of 2.25 MGD. Therefore, City Staff and the City Attorney have been working on drafting an agreement with CDI to modify these limits to better align the permitted amount with CDI's current flow discharge levels due to existing production demands at their facility.

CDI has two operational efficiency projects planned and is currently seeking building permits for both. As part of the review process, City staff advised CDI that before these building permits could be issued, they would need to bring their permitted wastewater discharge flow up to the level they are currently utilizing. The agreement outlined to address this requiremen...

Click here for full text